India Reaches 300 GW Non-Fossil Electricity Capacity Milestone
India has crossed 300 GW of installed non-fossil fuel-powered electricity generation capacity, as reported on 21 October 2026 by News On AIR. The milestone reflects a sustained build-up across renewable energy segments, including hydroelectric power, which remains a substantial part of the country's clean energy base.
The announcement provides context for a large and active hydel-based power project pipeline that continues to move through planning, approvals and construction stages across multiple Indian states.
Scale of the Hydel Project Pipeline
Projects India tracks 2,127 live hydel-based power projects across India, of which three were added to the database in the last 90 days. The pipeline spans a wide range of stages, from early planning through to completed projects, and covers both conventional run-of-river hydroelectric schemes and the fast-growing pumped storage segment.
Stage breakdown of tracked projects is as follows:
| Stage | Number of Projects |
|---|---|
| Under Approvals | 1,069 |
| Construction Started | 264 |
| Completed | 247 |
| Planning | 208 |
| Hold | 142 |
| Approvals Received | 70 |
With over half the tracked projects still under approvals and a further 208 in planning, a significant volume of procurement and construction activity is yet to come to market. The 264 projects currently in construction represent near-term demand for civil, mechanical and electrical contractors.
Geography: Where Hydel Activity Is Concentrated
Himachal Pradesh and Arunachal Pradesh together account for the largest share of tracked hydel projects, with 437 and 415 projects respectively. Uttarakhand follows with 259, while Maharashtra has 182, Jharkhand 98, and Madhya Pradesh 76. The concentration in Himalayan states reflects the availability of river systems suited to run-of-river projects, while Maharashtra's pipeline is increasingly shaped by pumped storage schemes.
Selected Projects Currently in the Pipeline
Among the projects tracked by Projects India, several large-value schemes are at active stages of development:
| Project | Promoter | Location | Value (Rs crore) | Stage |
|---|---|---|---|---|
| Hydel Power Project, Sileru | APGENCO | Visakhapatnam, Andhra Pradesh | 11,054 | Approvals Received |
| Pumped Storage Project, Sonbhadra | Jhariya Ananturja Private Limited | Sonbhadra, Uttar Pradesh | 7,457.68 | Under Approvals |
| Hydroelectric Power Project, Pune | Adani Renewable Energy Fifty Two Limited | Pune, Maharashtra | 7,048 | Under Approvals |
| Pumped Hydropower Storage, Sirohi | Avaada Group | Sirohi, Rajasthan | 5,800 | Under Approvals |
| Shongtong Karcham HEP | Himachal Pradesh Power Corporation Limited | Kinnaur, Himachal Pradesh | 2,807 | Construction Started |
| Bhivpuri Pumped Storage Project | Tata Power | Raigad, Maharashtra | 2,470 | Construction Started |
| Panari Pumped Storage Project | Sri Siddharth Infratech & Services (I) Private Limited | Satna, Madhya Pradesh | 2,671.75 | Under Approvals |
| Dikhu Hydro Power Project Dam-III | Manu Energy Systems Private Limited | Nagaland | 1,950 | Under Approvals |
| Thana Plaun HEP | Himachal Pradesh Power Corporation Limited | Mandi, Himachal Pradesh | Not recorded | Approvals Received |
| Bhavali Pumped Storage Project | JSW Energy PSP Two Limited | Thane, Maharashtra | Not recorded | Under Approvals |
For a fuller view of hydel and broader power sector projects tracked across India, including stage and promoter details, readers can access the Projects India database.
What this means for suppliers and contractors
The 300 GW non-fossil capacity milestone signals that India's energy transition is advancing at scale, and the hydel segment remains a material contributor. For suppliers and contractors, the pipeline data points to several practical conclusions.
The 1,069 projects currently under approvals represent the next wave of procurement. Suppliers of turbines, penstock pipes, civil construction services and electrical equipment should be identifying promoters and projects at this stage now, ahead of tenders being issued. There are currently no open tenders recorded in the Power Projects sector on the Projects India platform, making early-stage project intelligence particularly valuable for positioning ahead of formal procurement.
Geographically, Himachal Pradesh and Arunachal Pradesh dominate the pipeline and will continue to drive demand for specialist mountain-terrain contractors, tunnel boring equipment and remote logistics capacity. Maharashtra's growing pumped storage cluster — with projects from Tata Power, JSW Energy and others — points to a parallel opportunity in that state for contractors experienced in off-stream reservoir construction and high-voltage interconnection works.
The 264 projects already in construction require immediate attention from equipment suppliers and subcontractors seeking near-term order flow. The 70 projects at the approvals-received stage are the closest to moving into active procurement and merit close monitoring.
Readers tracking live tenders in the power sector can do so via the Projects India tenders page. Related recent activity in the power sector includes HCC winning a Rs 524.17 crore contract from NHPC for the Salal Power Station, which illustrates the contracting activity already under way at operating hydel assets.
Frequently asked questions
How many hydel power projects are tracked in India?
Projects India tracks 2,127 live hydel-based power projects across India. Of these, 1,069 are under approvals, 264 are in construction, 247 are completed, 208 are in planning, 142 are on hold, and 70 have received approvals.
Which states have the most hydroelectric projects in India?
Himachal Pradesh leads with 437 tracked hydel projects, followed by Arunachal Pradesh with 415 and Uttarakhand with 259. Maharashtra has 182, Jharkhand 98, and Madhya Pradesh 76, according to Projects India data.
What is the status of India's non-fossil fuel electricity capacity?
India crossed 300 GW of installed non-fossil fuel-powered electricity generation capacity, as reported by News On AIR on 21 October 2026. No further breakdown by technology or state was available from the single headline source.
What large pumped storage projects are under development in India?
Projects India tracks several large pumped storage schemes, including a Rs 7,457.68 crore project in Sonbhadra, Uttar Pradesh, a Rs 5,800 crore project in Sirohi, Rajasthan, and Tata Power's Rs 2,470 crore Bhivpuri project in Maharashtra, which has started construction.