Upcoming Water Supply Projects in India: Pipeline & EPC Leads
Projects India tracks 7,510 upcoming water supply and sewerage projects across India, with a combined recorded cost of around Rs 5.02 lakh crore. This report covers the largest schemes, active states, project stages and what they mean for EPC contractors and suppliers.
9 min read · 1,651 words
Projects India currently tracks 7,510 upcoming water supply and sewerage projects across India, of which 533 are verified with confirmed promoter and cost details. The combined recorded cost of projects in this scope stands at approximately Rs 5.02 lakh crore. In the last 90 days alone, 17 new projects were added to our database — nearly three times the six added in the equivalent period before that — signalling a clear acceleration in scheme activity. These span everything from bulk water transmission pipelines and 24x7 water supply distribution networks to sewage treatment plants, desalination facilities and waste water recycling units.
Upcoming water supply projects in India: at a glance
| Metric | Figure |
|---|---|
| Total upcoming projects tracked | 7,510 |
| Verified projects | 533 |
| Combined recorded project cost | ~Rs 5.02 lakh crore |
| Projects added in last 90 days | 17 |
| Projects currently under construction | 1,450 |
| Projects under approvals | 5,367 |
| Top state by project count | Uttar Pradesh (769) |
| Most active promoter | Uttar Pradesh Jal Nigam (624 projects) |
Largest upcoming water supply projects in India
The table below lists the highest-value schemes currently tracked by Projects India across the water and sewerage pipeline and distribution scope.
| Project | Promoter | Location | Cost | Stage |
|---|---|---|---|---|
| Water & Sewerage Pipeline & Distribution Project | Telangana Drinking Water Supply Corporation Limited | Telangana | Rs 42,853 crore | Construction Started |
| Waste Water Treatment Plant Project | SUEZ Group | Worli, Mumbai, Maharashtra | Rs 5,812 crore | Construction Started |
| Water & Sewerage Pipeline & Distribution Project | Municipal Corporation of Greater Mumbai | Mumbai, Maharashtra | Rs 3,900 crore | Construction Started |
| Sea Water Desalination Project | Chennai Metropolitan Water Supply and Sewerage Board | Perur, Chennai, Tamil Nadu | Rs 5,830 crore | Hold |
| Water & Sewerage Pipeline & Distribution Project | Bangalore Water Supply and Sewerage Board | Bengaluru, Karnataka | Rs 5,500 crore | Early / Announced |
| Water, Sewage & Effluent Treatment Project | Puducherry Urban Development Agency | Pondicherry, Maharashtra | Rs 4,966 crore | Under Approvals |
| Water & Sewerage Pipeline & Distribution Project | Hyderabad Metro. Water Supply and Sewerage Board | Keshavapuram, Hyderabad, Telangana | Rs 4,396 crore | Under Approvals |
| Water Supply Project | PNC Infratech | Pilibhit, Uttar Pradesh | Rs 3,717 crore | Approvals Received |
| Water Supply Project | PNC Infratech | Sambhal, Uttar Pradesh | Rs 3,717 crore | Under Approvals |
| Water Supply Project | PNC Infratech | Rampur, Uttar Pradesh | Rs 3,717 crore | Under Approvals |
| Water Supply Project | PNC Infratech | Budaun, Uttar Pradesh | Rs 3,717 crore | Under Approvals |
| Water Supply Project | PNC Infratech | Kannauj, Uttar Pradesh | Rs 3,717 crore | Under Approvals |
| Water Supply Project | PNC Infratech | Amroha, Uttar Pradesh | Rs 3,717 crore | Under Approvals |
| Water & Sewerage Pipeline & Distribution Project | National Water Development Agency | Kolar, Karnataka | Rs 3,508 crore | Under Approvals |
Three features stand out from this list. First, the Telangana Drinking Water Supply Corporation's statewide scheme — at Rs 42,853 crore — dwarfs every other single entry in the scope and is already under construction, meaning civil, pipe and electromechanical procurement is live or imminent. Second, PNC Infratech appears as promoter for six district-level water supply schemes across Uttar Pradesh, all in a similar cost band of Rs 3,717 crore each, suggesting a cluster of standardised EPC packages that suppliers can target with a single proposal format. Third, the Chennai desalination project remains on hold, so it is in the pipeline but not yet generating procurement activity.
For a fuller view of water and sewerage pipeline and distribution projects in India, including contact details and tender documents, the Projects India database provides granular records for each scheme.
Where are upcoming water supply projects concentrated?
The geographic spread is wide but far from uniform, as the chart below shows.
Uttar Pradesh leads with 769 projects, followed by Bihar (723), Maharashtra (705) and Gujarat (703). Karnataka (636) and Jharkhand (500) are also significant. These six states account for a disproportionate share of total scheme volume, driven in large part by rural piped water programmes reaching smaller towns and gram panchayats. For equipment and material suppliers, this geography has practical consequences: logistics, warehousing and distributor networks in Lucknow, Patna, Pune, Ahmedabad, Bengaluru and Ranchi are likely to see sustained demand. Andhra Pradesh (331 projects) and Tamil Nadu (368 projects) carry a heavier share of large individual schemes relative to their project count, meaning fewer but higher-value opportunities in those states.
Contractors and consultants already working in Uttar Pradesh or Bihar will find the highest number of discrete tender opportunities; those targeting Maharashtra or Tamil Nadu should focus on the value and complexity of individual packages rather than volume. Our related article on water supply projects in Andhra Pradesh covers the southern pipeline in more detail.
Project stages: where in the cycle is the work?
Understanding stage distribution helps contractors and suppliers decide how early to engage, as the chart below shows.
The dominant stage across all projects in this scope is Under Approvals, with 5,367 entries — a large funnel of work that has been sanctioned or is awaiting statutory and financial clearances. This is the right moment for EPC contractors to register with promoters, build relationships and position pre-bid. Construction Started projects number 1,450, representing active sites where subcontractor and equipment procurement is ongoing. The Planning (380) and Early / Announced (120) categories represent the earliest-stage intelligence available, where suppliers of specialised equipment — flow meters, SCADA systems, pumping sets, water treatment membranes — can shape specifications before tenders are drafted. Only 63 projects are Near Completion, which suggests the sector is mid-cycle rather than winding down.
Who is driving the most projects?
The most active promoters reveal where procurement authority sits, as the chart below shows.
Uttar Pradesh Jal Nigam leads all promoters with 624 projects carrying a combined recorded cost of around Rs 9,200 crore. The Drinking Water and Sanitation Department, Jharkhand follows with 371 projects (Rs 7,976 crore), and the Public Health Engineering Department, Bihar has 331 projects (Rs 3,346 crore). On a cost-weighted basis, the Public Health Engineering Department, Rajasthan is notable: 213 projects with a combined recorded cost of roughly Rs 23,294 crore, implying a high average project value. The Delhi Jal Board (136 projects, Rs 11,389 crore), Tamil Nadu Water Supply and Drainage Board (148 projects, Rs 12,857 crore) and Karnataka Urban Water Supply and Drainage Board (158 projects, Rs 9,138 crore) are the key urban utility buyers. Suppliers targeting multiple state utilities should note that procurement processes, empanelment norms and standard specifications differ between state boards — engaging early through the right channel at each body matters.
Projects added to our database in the last 90 days
Our records show 17 new water and sewerage projects were added in the last 90 days. The water-specific additions from this period include:
- Water Treatment Plant, Dhuri, Punjab — Rs 47 crore, Construction Started. Promoter: Government of Punjab.
- Water Supply Pipeline Project, Triveni Thanga, Gujarat — Rs 151 crore, Approvals Received. Promoter: Government of Gujarat.
- Sewage Recycling Plant, Thiruvananthapuram, Kerala — Rs 45 crore, Under Approvals. Promoter: Kerala Water Authority.
- Water Treatment Plant, Thiruvananthapuram, Kerala — Rs 200 crore, Planning. Promoter: Kerala Water Authority.
The Kerala Water Authority is active on both projects simultaneously — a signal that Thiruvananthapuram is entering a capital-spending cycle in water infrastructure. The Gujarat pipeline project has already received approvals, putting it closer to tender issuance than the others. Contractors and pipe suppliers watching Gujarat should check live government tenders for the corresponding procurement notices. The broader set of 17 new additions also includes biomedical waste treatment facilities, which sit within the same scope but serve a specialised segment of the market.
What this means for suppliers and contractors
Different project stages call for different actions:
- Planning and Early / Announced stages: This is where specification influence is possible. Manufacturers of pumping equipment, pipe materials (DI, HDPE, GRP), water meters, chlorination systems and SCADA platforms should engage with the listed promoters to present technical standards and get products qualified. At this stage, no tender exists yet — meetings, technical seminars and product demonstrations are the right tools.
- Under Approvals: With 5,367 projects at this stage, it represents the largest pool for pre-bid positioning. EPC contractors should register on relevant state procurement portals, obtain empanelment where required and ensure financial and technical pre-qualification documents are current. Equipment suppliers should map which EPC firms are likely to bid on each scheme and open supply discussions early.
- Approvals Received and Construction Started: Active procurement. Civil contractors, pipe suppliers, pump and motor OEMs, electrical panel manufacturers, instrumentation firms and O&M service providers should be responding to tenders and quotation requests. The 1,450 projects under construction are generating real purchase orders now.
- 24x7 water supply and distribution networks involve a different supply chain from bulk transmission or treatment plant work, typically including metering, distribution management and pressure management equipment.
- Waste water treatment and sewage recycling plants — such as the Worli, Mumbai project (Rs 5,812 crore, construction started) — involve specialised civil, process, membrane and electrical subcontracts that differ from clean-water infrastructure. Firms with STP or WTP credentials should track these separately.
For a broader view of pipeline project opportunities across other sectors, our article on upcoming pipeline projects in India covers oil, gas and water leads together.
How to track these projects
Government portals publish individual tenders but do not consolidate scheme pipelines, promoter contacts, project costs and stage information in one place. Projects India aggregates exactly this — across all 84,976 projects it tracks nationally — and updates records as stage changes, tender awards and new announcements occur. Users can filter the water and sewerage pipeline and distribution projects database by state, stage, cost band and promoter to build a shortlist relevant to their geography and capability. A free sample project report is available to review the depth of information before subscribing. Sales teams and business-development managers who want structured lead lists rather than individual record lookups can explore the projects intelligence database for export and CRM-integration options. Teams responding to formal tenders can also use the AI tender intelligence tool to match tender documents against company profiles and flag relevant notices early.
Frequently asked questions
How many upcoming water supply projects are there in India?
Projects India tracks 7,510 upcoming water supply and sewerage projects across India as of November 2026, of which 533 are verified with confirmed promoter and cost details. Their combined recorded cost is approximately Rs 5.02 lakh crore.
Which states have the most water supply projects in India?
Uttar Pradesh leads with 769 projects, followed by Bihar (723), Maharashtra (705), Gujarat (703), Karnataka (636) and Jharkhand (500). These six states account for the largest share of total project volume in the water and sewerage scope tracked by Projects India.
What are the largest upcoming water supply projects in India?
The largest is a statewide water and sewerage project by the Telangana Drinking Water Supply Corporation at Rs 42,853 crore, already under construction. Other major schemes include a Rs 5,830 crore desalination plant in Chennai, a Rs 5,812 crore waste water treatment plant in Mumbai and a Rs 5,500 crore distribution project in Bengaluru.
What is the status of 24x7 water supply projects in India?
Many 24x7 water supply distribution schemes are at the Under Approvals stage, the largest single stage in Projects India's database with 5,367 entries in this scope. Construction-started projects number 1,450, meaning active procurement for pipes, meters, pumps and SCADA systems is ongoing on a significant number of sites.
Which agencies are the most active promoters of water supply projects in India?
Uttar Pradesh Jal Nigam leads with 624 projects (Rs 9,200 crore combined), followed by Jharkhand's Drinking Water and Sanitation Department (371 projects, Rs 7,976 crore) and Bihar's Public Health Engineering Department (331 projects, Rs 3,346 crore). Tamil Nadu Water Supply and Drainage Board and Delhi Jal Board are also major buyers.
How can contractors and suppliers find water supply tenders in India?
Projects India tracks water and sewerage projects from early planning through to construction, providing promoter contacts, project costs and stage updates. Users can filter by state, stage and cost band. A free sample project report is available, and live tender notices are listed separately in the tenders section.
Get the full list of 7,663 Water & Sewerage Pipeline & Distribution projects in India
- Project name, promoter, cost, stage and location
- Verified decision-maker contacts
- Updated daily — plus live tenders