New Captive Power Plant Projects in India: 2026 Leads
Projects India tracks 1,886 upcoming captive power plant projects across India, with a combined recorded cost of about Rs 15.81 lakh crore. Maharashtra, Chhattisgarh and Karnataka lead by project count.
10 min read · 1,880 words
Projects India currently tracks 1,886 upcoming captive power plant projects across India, of which 1,532 are marked verified. The combined recorded cost of projects with a known value stands at about Rs 15.81 lakh crore. Thirty-three new projects were added to our database in the last 90 days, compared with 31 in the 90 days before that, confirming a steady pipeline that is growing quarter on quarter.
Captive power plant projects in India — at a glance
| Metric | Figure |
|---|---|
| Upcoming projects tracked | 1,886 |
| Verified projects | 1,532 |
| Combined recorded project cost | ~Rs 15.81 lakh crore |
| New projects added (last 90 days) | 33 |
| New projects added (prior 90 days) | 31 |
| Projects under construction | 284 |
| Projects under approvals | 1,056 |
| Approvals received (ready to proceed) | 156 |
| Top state by project count | Maharashtra (281) |
| Total projects tracked nationally (all sectors) | 85,111 |
Largest upcoming captive power plant projects in India
The table below lists the highest-value upcoming projects in our database. Odisha, Chhattisgarh, Karnataka and Jharkhand account for most of the top entries by cost, reflecting the concentration of steel, aluminium and cement manufacturing in those states.
| Project | Promoter | Location | Recorded Cost | Stage |
|---|---|---|---|---|
| Captive Power Plant at Kamakhyanagar, Dhenkanal | Vedanta Limited | Dhenkanal, Odisha | Rs 1,28,000 crore | Under Approvals |
| Captive Power Project at Paradeep (New) | JSW Utkal Steel Limited | Paradeep, Odisha | Rs 65,000 crore | Construction Started |
| Coal Based Power Unit at Kalinga Nagar, Jajpur (Expansion) | Neelachal Ispat Nigam Limited | Jajpur, Odisha | Rs 61,769 crore | Under Approvals |
| Captive Power Plant at Kuduthini, Bellary | Uttam Galva Ferous Limited | Bellary, Karnataka | Rs 36,000 crore | Under Approvals |
| Captive Power Plant at Barenda Village, Ranchi (Unit III) | JSW Jharkhand Steel Limited | Ranchi, Jharkhand | Rs 35,000 crore | Hold |
| Captive Power Plant at Gokulpur, Paschim Medinipur | Rashmi Metallurgical Industry Private Limited | Paschim, West Bengal | Rs 30,000 crore | Construction Started |
| WHR & FBC Captive Power Plant at Hazaribagh, Ranchi | Jammu & Kashmir State Power Development Corporation Limited | Ranchi, Jharkhand | Rs 22,000 crore | Planning |
| Co-Generation Power Plant at Dhamni, Mungeli | Kusum Smelters Private Limited | Mungeli, Chhattisgarh | Rs 19,331 crore | Under Approvals |
| Captive Power Plant at Halavarthi, Koppal (Approvals Received) | Aaress Iron & Steel Limited | Koppal, Karnataka | Rs 18,000 crore | Approvals Received |
| Captive Power Project at Halavarthi Village, Koppal (Under Approvals) | Aaress Iron And Steel Limited | Koppal, Karnataka | Rs 18,000 crore | Under Approvals |
| CDCP Power Plant at Bhilai, Durg (Expansion) | Steel Authority of India Limited | Durg, Chhattisgarh | Rs 17,265 crore | Under Approvals |
| Coal Based Captive Thermal Power Plant at Butibori, Nagpur (Phase II) | Twin Star Display Technologies Limited | Nagpur, Maharashtra | Rs 16,500 crore | Under Approvals |
| Captive Power Plant at Nagarnar, Bastar | NMDC Limited | Bastar, Chhattisgarh | Rs 15,525 crore | Construction Started |
| Captive Power Plant at Gadchiroli, Maharashtra | Jayaswal Neco Industries Limited | Gadchiroli, Maharashtra | Rs 12,262 crore | Under Approvals |
| Captive Power Project at Angul, Odisha (New) | National Aluminium Company Limited | Angul, Odisha | Rs 12,000 crore | Under Approvals |
Several patterns stand out in this list. Steel producers — JSW Utkal Steel, Neelachal Ispat Nigam, Rashmi Metallurgical and Jayaswal Neco — dominate the high-value end, reflecting the energy intensity of integrated steel manufacturing. The JSW Utkal Steel project at Paradeep and the NMDC project at Bastar are already under construction, with expected completion in December 2027 and December 2026 respectively — making the NMDC project at Bastar an immediate opportunity for civil, mechanical and electrical contractors, with the JSW Utkal Steel project at Paradeep following in late 2027. Vedanta's project at Kamakhyanagar carries the highest recorded cost at Rs 1,28,000 crore and remains under approvals, signalling a long lead time before tendering opens. Explore the full list of captive power plant projects in India for decision-maker contacts and tender timelines.
Where are captive power plant projects concentrated?
As the chart below shows, project activity is not evenly spread — industrial heartlands account for the bulk of the pipeline.
Maharashtra leads with 281 projects, driven by its large base of cement, steel and chemical manufacturers spread across Vidarbha, Pune and the Konkan corridor. Chhattisgarh (230 projects) is dominated by steel and sponge iron producers who rely on captive coal-based and waste-heat-recovery power to remain cost-competitive. Karnataka (218) has seen significant activity from iron and steel players in the Bellary-Koppal belt, while Odisha (128) and Andhra Pradesh (125) reflect active primary metal industries. Uttar Pradesh (149) has a broader industrial base including cement, paper and sugar, all of which routinely commission captive or co-generation units.
For suppliers with a regional focus, Gujarat warrants particular attention: our database shows 97 upcoming projects in that state alone — a concentration that reflects the state's dense chemical, petrochemical and ceramic manufacturing clusters. Readers can filter by geography on the dedicated captive power plant projects in Gujarat page to see project-level detail for that state.
Project stages — what the pipeline looks like for EPC and equipment firms
Understanding where projects sit in the approval and construction cycle determines how early a supplier or contractor should engage. As the chart below shows, the pipeline is heavily weighted toward the early stages.
With 1,056 projects Under Approvals and a further 156 that have Approvals Received, the pipeline ahead of active tendering is substantial. Projects at the Approvals Received stage are typically the most actionable for equipment vendors and EPC contractors: regulatory clearances are in hand and procurement planning is underway. The 284 projects already under construction represent active sites requiring ongoing supply of structural steel, boilers, turbines, electrical switchgear, transformers, instrumentation and civil works. A further 284 are on hold, often pending financing closure or fuel linkage — these warrant monitoring rather than immediate pursuit. Only 61 are in the Planning stage, suggesting that most promoters who have an identified project have already moved into the approvals process.
The power projects sector overview on Projects India breaks the pipeline down further by fuel type and sub-sector for teams that need to filter by technology.
Most active promoters in the captive power space
Knowing which companies are serial developers helps suppliers and contractors prioritise relationship-building. As the chart below shows, a handful of industrial groups account for a disproportionate share of projects.
Ultratech Cement leads by project count with 21 captive power projects carrying a combined recorded cost of about Rs 22,860 crore — consistent with the cement industry's dependence on uninterrupted, low-cost power. Jayaswal Neco Industries Limited follows with 15 projects (combined cost about Rs 43,524 crore), all in the steel sector. Shree Cement Limited and Wonder Cement are also active multi-project developers, reflecting the cement industry's systematic approach to captive generation. Rungta Mines Limited (11 projects, about Rs 26,236 crore) and Ardent Steel Limited (6 projects, about Rs 15,373 crore) represent the mining-linked steel segment. For equipment suppliers, these repeat developers are priority accounts: a relationship built on one project can carry through to the next expansion cycle.
Projects added to our database in the last 90 days
Thirty-three new captive power projects entered our records in the last 90 days. The selection below illustrates the range of sectors, geographies and project sizes entering the pipeline right now.
- Captive Thermal Power Plant, Maharashtra (New) — Lloyds Metals, Rs 3,240 crore, Approvals Received. One of the more advanced new entrants, with clearances already in hand.
- Captive Power Project at Tirupati, Andhra Pradesh (New) — PCBL Limited, Rs 3,718 crore, Under Approvals. A carbon-black manufacturer adding captive generation capacity in Andhra Pradesh.
- Captive Power Plant at Raipur, Chhattisgarh (New) — Sambhv Steel Tubes Limited, Rs 360 crore, Construction Started. A smaller but immediately active project where civil and mechanical supply opportunities are open now.
- Captive Power Plant at West Singhbhum, Jharkhand (New) — Shivans Steel Private Limited, Under Approvals. Location in a mineral-rich district points to steel-linked captive demand.
- Captive Power Plant at Chandil, Jharkhand — Narsingh Ispat Limited, Approvals Received. Another steel-sector project with clearances secured.
- Co-Generation Power Plant at Bejjanki, Telangana (Expansion) — Whitefield Bio Products Private Limited, Planning. An agro-industrial co-generation project in early development.
- Captive Power Project at Chamorshi, Maharashtra (New) — Saffron Hill Metals Private Limited, Planning. Gadchiroli district, in line with the state government's push to industrialise the region.
- Captive Power Project at Borgaon, Madhya Pradesh (Expansion) — Ukr Industries Limited, Under Approvals. An expansion rather than a greenfield, suggesting the promoter has an established operational base.
These recent additions span steel, carbon black, agro-processing and metals — a reminder that captive power is a cross-sector requirement, not limited to any single industry. Teams tracking all upcoming projects in India can filter by sector, state and stage to surface opportunities matching their supply scope.
What this means for suppliers and contractors
The stage of a project determines what it is buying and from whom.
- Planning and Early / Announced: These projects are acquiring land, commissioning feasibility studies and engaging consultants for DPR preparation. Opportunities at this stage are for project management consultants, geotechnical survey firms and technology licensors.
- Under Approvals: With 1,056 projects at this stage, environmental clearance, statutory consents and fuel linkage discussions are underway. Equipment vendors who pre-qualify now — supplying budgetary quotations for boilers, turbines, cooling towers and electrical systems — can influence equipment specifications before tenders are issued.
- Approvals Received: The 156 projects here are actively preparing detailed engineering and procurement plans. EPC contractors, civil contractors, structural steel and PEB suppliers, transformer manufacturers, DG set suppliers and balance-of-plant vendors should be in active conversation with promoter engineering teams at this stage.
- Construction Started: The 284 active construction sites require immediate supply of structural fabrication, piping, instrumentation, cables, switchgear and site services. PEB (pre-engineered building) structures for auxiliary buildings, control rooms and warehouses are routinely procured at this stage — an entry point for PEB supply and construction specialists referenced in related searches.
- Hold: The 284 projects on hold are worth monitoring for reactivation signals. Financing closures, fuel linkage awards or policy changes can move a held project to active procurement within months. Maintaining contact with the promoter's project team during this period keeps contractors and vendors positioned ahead of any restart.
Cement companies such as Ultratech, Shree Cement and Wonder Cement procure in bulk across multiple sites — a single vendor approval can unlock supply orders across their entire portfolio. Steel sector projects, which dominate the high-value end of this pipeline, typically involve waste-heat recovery, blast-furnace gas and coal-based units, requiring specialised boiler and turbine technology alongside conventional EPC capability. Teams looking for live government tenders in the power sector can filter by state and project type to identify active procurement notices running in parallel with these project leads.
How to track these captive power plant projects in India
Public sources — environmental clearance portals, stock exchange filings and industry press — capture a fraction of the pipeline and rarely carry decision-maker contacts, project cost estimates or procurement timelines in one place. Projects India consolidates verified project-level data — promoter, location, cost, stage, expected completion and contact details — across 1,886 captive power projects, updated continuously as projects move through approvals, tendering and construction. Teams that need to build a target account list by state, fuel type or project stage can use the projects intelligence database with custom filters, or request a free sample project report to see the depth of data available before subscribing. The contractor and supplier directory (VendorConnect) complements project tracking by helping firms identify co-bidding partners or subcontractors active in specific geographies.
Frequently asked questions
How many captive power plant projects are currently tracked in India?
Projects India tracks 1,886 upcoming captive power plant projects across India as of November 2026, of which 1,532 are verified. The combined recorded cost of projects with a known value is about Rs 15.81 lakh crore. Thirty-three new projects were added in the last 90 days.
Which states have the most captive power plant projects in India?
Maharashtra leads with 281 upcoming captive power projects, followed by Chhattisgarh (230), Karnataka (218), Uttar Pradesh (149), Odisha (128) and Andhra Pradesh (125). Gujarat has 97 projects. The concentration reflects the distribution of steel, cement, aluminium and chemical manufacturing across these states.
Which companies have the most captive power plant projects in India?
Ultratech Cement Limited leads with 21 projects (combined recorded cost about Rs 22,860 crore), followed by Jayaswal Neco Industries Limited with 15 projects (about Rs 43,524 crore). Shree Cement, Wonder Cement, Rungta Mines and Ardent Steel are also among the most active repeat developers in this space.
What is the largest upcoming captive power plant project in India by cost?
By recorded cost in the Projects India database, the Captive Power Plant Project at Kamakhyanagar, Dhenkanal, Odisha by Vedanta Limited carries the highest value at Rs 1,28,000 crore. It is currently Under Approvals with no confirmed completion date published yet.
What equipment and services do captive power plant projects buy, and at which stage?
Projects under approvals buy budgetary quotations and pre-qualification submissions. Once approvals are received, detailed engineering, boilers, turbines, transformers and civil contractors are engaged. Construction-stage projects (284 currently active) procure structural steel, PEB structures, instrumentation, cables and site services on an ongoing basis.
Are there captive power plant projects in Gujarat?
Yes. Projects India records 97 upcoming captive power plant projects in Gujarat, driven by the state's dense base of chemical, petrochemical and ceramic manufacturers. Project-level details including promoter names, costs and stages are available through the dedicated Gujarat captive power projects page on Projects India.
Get the full list of 2,464 Captive Power projects in India
- Project name, promoter, cost, stage and location
- Verified decision-maker contacts